The seaport area has been invested by Sao Do Group and developed according to the concept of “modern seaport” when associated with the Industrial Park and Economic Zone.
Seaport area:
- Scale: 07 container terminals, general cargo.
- Vessel reception: up to 40,000DWT.
- Total loading and unloading capacity: 20 million tons/year
- Implementation progress: Phase 1 (first quarter of 2018) has put into operation 02 container terminals.
Warehouse / yard (logistics):
Warehouse / yard area (logistics) is planned as a logistics area for the seaport system in Dinh Vu peninsula and Nam Dinh Vu industrial land…
- Site: has been leveled, ready to hand over.
- Available area for rent: > 50ha phase 1
- Handing over the leased land: elevation ±4.5; tightness k90.
- Utilities in the Area: ready and connected to the foot of the fence of the leased land
- Power supply: phase 1 capacity 2×63 MVA.
- Water supply: 30,000 m3/day
- Wastewater treatment plant: phase 1 with a capacity of 10,000 m3/day.
- Other utilities: providing seaport services, banks, post offices, on-site customs…